Gravel Banding

We were contracted by Handsworth Golf Club to install secondary drainage on the green.

Method

  • We used our trencher to excavate drainage channels in the green
  • The trenches were backfilled with 2-6mm gravel to 100mm below the surface
  • Rootzone was used to top the gravel bands up to the surface
  • The Rootzone was firmed up and consolidated

 

Client
Handsworth Golf Club
Year
2019
We Did
Installed gravel bands